Project Description:
GLOUCESTER- BRIDGE RECONSTRUCTION, G-05-002, WESTERN AVENUE OVER BLYNMAN CANAL
The Blynman Bridge carries Route 127 (Western Ave) over the Blynman Canal. The bridge is a vital link as one of two bridges providing access to Gloucester. The bridge has passed its useful life and is in an advanced state of deterioration. This project was initiated to develop a viable bridge replacement for this location. The scope of the project includes replacement of the existing movable bridge with a new movable bridge. To achieve this and maintain traffic, a temporary bypass will be built immediately to the south of the bridge, which will include a movable span over the navigation channel. Navigation channel closures will be required during portions of the project and coordinated with the United States Coast Guard.
Location:
  • City of Gloucester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Joseph Breen
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2030 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • G05002 
    See the Milestone Details tab for additional Project information
    Planned Federal FY: 2030
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: GLOUCESTER
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $16,553,014.40
    State Cost: $4,138,253.60
    Total Cost: $20,691,268.00