MILTON- RECONSTRUCTION ON GRANITE AVENUE, FROM NEPONSET RIVER TO SQUANTUM STREET (5,000 FEET)
Work consists of reconstructing Granite Avenue for the support of the Central Maintenance Facility and Highway Operations Center relocation and construction. See #608405. The limits are from the Southeast Expressway ramps near the Neponset River extending southerly to Squantum Street. 2 - 12 foot travel lanes, a 5 foot bicycle lane, and 5 foot sidewalk on both sides are proposed.
Location:
  • Town of Milton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $3,665,146.26
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 25% Package Received (as of 02/10/2017 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/11/2015
    Project Initiation Form PIF Entered 12/11/2015
    Project Initiation Form PRC Submitted 12/11/2015
    Project Review Committee PRC Approved 12/11/2015
    Project Management
    25% Design 25% Package Received 02/10/2017
    Consultant Contract Process Scope to DE 02/02/2016
    Consultant Contract Process Workhours Approved 02/19/2016