Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BELCHERTOWN- IMPROVEMENTS & RELATED WORK ON ROUTES 202 & 21, FROM TURKEY HILL ROAD TO SOUTH MAIN STREET (1.2 MILES)
This is a complete streets project that will improve accommodations for all users. The roadway will be resurfaced and widened for improved bicycle accommodations, new and reconstructed sidewalks are proposed for improved pedestrian access, and new wheelchair ramps and crosswalks will be installed. Intersection improvements at Stadler/Front streets. Improvements will include turn lanes and possible new traffic signal.
Location:
  • Town of Belchertown
  • Construction Begins: Spring 2020
    Resident Engineer: Michael DeSimone
    Construction Bid Price: $4,361,088.50
    District: District 2

    Contracts (1) Progress
    # 109408 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 202/21 (State & Maple Streets) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2016
    Project Initiation Form PIF Entered 01/27/2016
    Project Initiation Form PRC Submitted 01/27/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 08/17/2019
    Project Management
    100% Design 100% Package Received 01/14/2019
    100% Design 100% Package Comments to DE 02/26/2019
    25% Design 25% Package Received 05/17/2017
    25% Design 25% Package Comments to DE 12/21/2017
    25% Design Design Public Hearing 01/10/2018
    75% Design 75% Package Received 05/04/2018
    75% Design 75% Package Comments to DE 08/22/2018
    Final Design PS&E Received 07/01/2019
    Final Design PS&E to FAPRO 08/05/2019