Project Description:
NORTHAMPTON- ROCKY HILL GREENWAY MULTI-USE TRAIL, FROM THE MANHAN RAIL TRAIL TO ROCKY HILL ROAD (0.4 MILES)
The proposed project consists of the construction of 0.4 miles of multi-use trail starting at the Manhan Rail Trail traveling northerly to Rocky Hill Road. The proposed path will be 10 foot minimum width consisting of an asphalt mix riding surface. In addition, the proposed project will include the construction of parking, trail heads, and the installation of wood safety rail, safety signing, and pavement markings. Minor improvements will be made to 760' of Rocky Hill Road, including restriping for improved bicycle accommodations, improved sidewalk, and wheelchair ramps.
Location:
  • City of Northampton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2025
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $2,500,501.17
    Estimated Total Federal Participating Construction Cost: $2,714,089.38
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: PS&E Received - Resub 3 (as of 10/11/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • Changed from CMAQ to HPP via STIP Action 1.
  • Category FA - High Priority Projects (HPP)
    Federal Cost: $2,277,375.20
    State Cost: $569,343.80
    Total Cost: $2,846,719.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2016
    Project Initiation Form PIF Entered 01/28/2016
    Project Initiation Form PRC Submitted 01/28/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    100% Design 100% Package Received 01/15/2021
    100% Design 100% Package Comments to DE 04/20/2021
    100% Design 100% Package Received - Resub 1 06/10/2022
    100% Design 100% Package Received - Resub 1 06/10/2022
    100% Design 100% Package Received - Resub 2 08/18/2023
    25% Design 25% Package Received 08/03/2016
    25% Design 25% Package Comments to DE 09/23/2016
    25% Design 25% Package Received - Resub 2 07/11/2018
    25% Design Design Public Hearing 03/07/2019
    75% Design 75% Package Received 01/10/2020
    75% Design 75% Package Comments to DE 03/27/2020
    Final Design PS&E Received - Resub 1 04/30/2024
    Final Design PS&E Received - Resub 3 10/11/2024
    Consultant Contract Process NTP Issued 01/20/2015