Project Description:
GREENFIELD- INTERSECTION IMPROVEMENTS AT TWO LOCATIONS, ROUTE 2 AND COLRAIN ROAD & ROUTE 2 AND BIG Y ENTRANCE
The project involves traffic signal and intersection improvements at the intersections of Route 2 and Colrain Road and Route 2 at the Big Y entrance. The signal at Colrain Road will be a signal reconstruction, and the Big Y entrance will be a new signal. Other improvements to be considered include shoulder widening, new sidewalks and wheelchair ramps, pavement markings, drainage, and signage.
Location:
  • Town of Greenfield
  • Construction Begins: Summer 2023
    Resident Engineer: Liam Pitrat
    Construction Bid Price: $2,495,960.75
    District: District 2

    Contracts (3) Progress
    # 123405 -- Construction Contract
    Intersection Improvements at Two Locations, Route 2 and Colrain Road & Route 2 and Big Y Entrance 40% Complete
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/20/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2016
    Project Initiation Form PIF Entered 01/27/2016
    Project Initiation Form PRC Submitted 01/27/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 07/29/2023
    Project Management
    100% Design 100% Package Received 04/12/2023
    25% Design 25% Package Received 06/05/2020
    25% Design 25% Package Comments to DE 09/14/2020
    25% Design 25% Package Received - Resub 5 04/15/2022
    25% Design Design Public Hearing 02/22/2022
    75% Design 75% Package Received 07/20/2022
    75% Design 75% Package Comments to DE 09/01/2022
    Final Design PS&E Received 06/06/2023
    Final Design PS&E to FAPRO 07/17/2023
    Consultant Contract Process NTP Issued 02/21/2019