Project Description:
ATHOL- INTERSECTION IMPROVEMENTS AT ROUTE 2A AND BROOKSIDE ROAD
The project involves traffic signal and intersection improvements at Route 2A and Brookside Road. Improvements to be considered are shoulder widening, new sidewalks, improved lane usage markings, drainage, and signage. Improvements will be based on recommendations from a Road Safety Audit once conducted.
Location:
  • Town of Athol
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Alolade O Campbell
    Estimated Total Contract Cost: $1,454,800.00
    Estimated Total Federal Participating Construction Cost: $1,544,720.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 08/31/2022 )

    Contracts (1) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: ATHOL
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,384,068.80
    State Cost: $346,017.20
    Total Cost: $1,730,086.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2016
    Project Initiation Form PIF Entered 01/27/2016
    Project Initiation Form PRC Submitted 01/27/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    Consultant Contract Process NTP Issued 08/31/2022