Project Description: |
ATHOL- INTERSECTION IMPROVEMENTS AT ROUTE 2A AND BROOKSIDE ROAD
The project involves traffic signal and intersection improvements at Route 2A and Brookside Road. Improvements to be considered are shoulder widening, new sidewalks, improved lane usage markings, drainage, and signage. Improvements will be based on recommendations from a Road Safety Audit once conducted.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2027 |
Project Manager: | Alolade O Campbell |
Estimated Total Contract Cost: | $1,454,800.00 |
Estimated Total Federal Participating Construction Cost: | $1,544,720.00 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization. |
District: | District 2 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 08/31/2022 ) |
|
Bridges
|
|
|
|