Project Description:
LOWELL- RECONSTRUCTION AND REHABILITATION OF FIVE BRIDGES (ENEL BRIDGES) TIGER GRANT
The project will include the complete replacement of two bridges, repairs to four bridges including new deck, beams and rail replacement for two of these bridges and deck repairs and rail replacement for two of these bridges. In conjunction with the TIGER project, Enel has agreed to replace one bridge at its own expense. The eighth bridge was replaced in 2014 in response to an emergency structural failure. In all cases, the new bridges will provide enhanced pedestrian and bicycle accommodations and will remove posted weight restrictions to allow transit buses, emergency vehicles, and commercial trucks to utilize the crossings. All of the replacement bridges will be designed in partnership with the Lowell National Historical Park and Lowell Historic Board to complement the historic canal system.
Location:
  • City of Lowell
  • Construction Begins: Spring 2018
    Resident Engineer: Daniel Boland
    Construction Bid Price: $12,747,732.46
    District: District 4

    Contracts (2) Progress
    # 101888 -- Construction Contract
    Bridge Replacement and Rehabilitation of 5 (ENEL) Canal Bridges of the Merrimack River (TIGER Grant). Completed
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/27/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/11/2016
    Project Initiation Form PIF Entered 01/11/2016
    Project Initiation Form PRC Submitted 01/11/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 08/12/2017
    Project Management
    100% Design 100% Package Received 06/01/2017
    25% Design 25% Package Received 12/07/2016
    75% Design 75% Package Received 04/19/2017
    Final Design PS&E Received 07/17/2017
    Final Design PS&E to FAPRO 07/24/2017