Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SANDWICH- CONSTRUCTION OF SHARED USE PATH ALONG SERVICE ROAD FROM ROUTE 130 TO CHASE ROAD
In 2013, National Grid (NGRID, an international electricity and gas company, approached the Town of Sandwich with a request to construct and maintain a 20” gas main in the roadside area between the Service Road pavement and the Mid-Cape Highway right-of-way. The Town of Sandwich, as part of the local permit process, mandated that a variety of public betterments be included in the project. One such betterment requires National Grid to include tree removal and rough grading along the proposed gas line alignment that would serve as a base for constructing this first phase of a multi-phase shared-use path project from Route 130 to Chase Road.
Location:
  • Town of Sandwich
  • Construction Begins: Autumn 2022
    Resident Engineer: Michelle Muller
    Construction Bid Price: $8,932,505.20
    District: District 5
    Current Status: The contractor is on site installing drainage structures and grading slopes along Service Road. Sedimentation removal and slope repairs will be performed adjacent to Route 6 EB on Friday, April 5th, at Mile Marker 61. Paving operations along the Shared Use path are scheduled for April 8-10. Fence and Wood Rail installations are in progress, as well as aerial utility work by third party utility companies. Intermittent single lane closures with alternating traffic along Service Road is anticipated while Shared Use Path paving operations are taking place. Normal work hours are Monday through Friday, 7:00 Am to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/02/2024)

    Contracts (2) Progress
    # 120083 -- Construction Contract
    Construction of a Shared Use Path along a Section of Service Road 71% Complete
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/26/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/12/2016
    Project Initiation Form PIF Entered 01/28/2016
    Project Initiation Form PRC Submitted 01/28/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 08/27/2022
    Project Management
    100% Design 100% Package Received 04/19/2022
    100% Design 100% Package Comments to DE 05/20/2022
    25% Design 25% Package Received 04/17/2019
    25% Design 25% Package Comments to DE 04/01/2020
    25% Design Design Public Hearing 01/01/2021
    75% Design 75% Package Received 09/17/2021
    Final Design PS&E Received 07/05/2022
    Final Design PS&E to FAPRO 07/27/2022
    Final Design PS&E Received - Resub 1 07/27/2022