Project Description:
EASTHAMPTON- IMPROVEMENTS AND RELATED WORK ON ROUTE 10, FROM WEST STREET TO THE NORTHAMPTON TOWN LINE
This is a complete streets project that will improve accommodations for all users. The roadway will be resurfaced and widened for improved bicycle accommodations, new and reconstructed sidewalks are proposed for improved pedestrian access, and new wheelchair ramps and crosswalks will be installed. Other work will consist of improved drainage, signage, pavement markings, and other incidentals.
Location:
  • Town of Easthampton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2028
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $5,303,800.00
    Estimated Total Federal Participating Construction Cost: $5,758,750.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 04/26/2023 )

    Contracts (1) Progress
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: EASTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / YOE $6,449,800 / 29.5 TEC / Pres 25% STBG
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,159,840.00
    State Cost: $1,289,960.00
    Total Cost: $6,449,800.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/12/2016
    Project Initiation Form PIF Entered 01/28/2016
    Project Initiation Form PRC Submitted 01/28/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    Consultant Contract Process NTP Issued 04/26/2023