Project Description:
TEMPLETON- RECONSTRUCTION OF ROUTE 68, FROM KING PHILLIP TRAIL (ROUTE 202) NORTH TO THE PHILLIPSTON TOWN LINE (2.65 MILES)
This project will consist of full-depth reconstruction and pavement widening of Royalston Road (Rte. 68) from the junction of Route 202 north to the Phillipston town line. Other work will include will include widening of the roadway to provide 5' bike lanes, improved drainage, and the replacement of 2 large culvert crossings.
Location:
  • Town of Templeton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Adetoyin Ayoola Olaoye
    Estimated Total Contract Cost: $9,742,418.01
    Estimated Total Federal Participating Construction Cost: $10,319,450.63
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 2
    Current Status: 75% Package Received - Resub 1 (as of 09/30/2020 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: TEMPLETON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,238,683.20
    State Cost: $1,309,670.80
    Total Cost: $6,548,354.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/12/2016
    Project Initiation Form PIF Entered 01/29/2016
    Project Initiation Form PRC Submitted 01/29/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    25% Design 25% Package Received 04/05/2017
    25% Design 25% Package Comments to DE 04/12/2017
    25% Design Design Public Hearing 12/12/2018
    75% Design 75% Package Received 12/20/2019
    75% Design 75% Package Comments to DE 05/25/2020
    75% Design 75% Package Received - Resub 1 09/30/2020