Project Description:
RUTLAND- RECONSTRUCTION OF ROUTE 56 (POMMOGUSSETT ROAD)
The proposed improvements include pavement rehabilitation with minor box widening, from Route 122A to the intersection of Brunelle Drive, a distance of 1.0 mile. The project invovles improvements to pedestrian and bicycle accommodations, including sidewalk reconstruction and extension. Additional improvements include repair or replacement of a culvert, drainage upgrades, new signage and pavement markings. The proposed cross section would include 11’ travel lanes, 5’ shoulders and a 5.5’ HMA sidewalk on one side with granite curb.
Location:
  • Town of Rutland
  • Construction Begins: Autumn 2022
    Resident Engineer: Roger Wykes
    Construction Bid Price: $6,580,524.00
    District: District 3

    Contracts (2) Progress
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 120184 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Culvert Replacement) on a Section of Route 56 (Pommogussett Road) 66% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/09/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/14/2016
    Project Initiation Form PIF Entered 01/14/2016
    Project Initiation Form PRC Submitted 01/14/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 10/09/2021
    100% Design 100% Package Comments to DE 11/12/2021
    100% Design 100% Plans Approved 12/09/2021
    100% Design 100% Plans Complete 12/09/2021
    25% Design 25% Package Received 04/24/2017
    25% Design 25% Package Comments to DE 02/26/2019
    25% Design 25% Package Received - Resub 1 01/16/2020
    25% Design 25% Package Received - Resub 2 01/30/2020
    25% Design Design Public Hearing 01/26/2021
    75% Design 75% Package Received 05/03/2021
    75% Design 75% Package Comments to DE 06/29/2021
    75% Design 75% Plans Approved 09/08/2021
    75% Design 75% Plans Complete 09/08/2021
    Final Design PS&E Received 06/07/2022
    Final Design PS&E Received - Resub 1 08/05/2022
    Final Design PS&E Received - Resub 2 08/23/2022