Project Description:
WEBSTER- INTERSECTION IMPROVEMENTS AT I-395 RAMPS (EXIT 3) AT ROUTE 16 (EAST MAIN STREET) AND SUTTON ROAD
The proposed project involves installation of traffic signals or roundabouts at the I-395 NB and SB ramps at Route 16, including resurfacing and geometric improvements. Additional work includes widening for bicycle and pedestrian accommodation, specifically reconstructing existing sidewalk and construction of new sidewalk sections. The widening and sidewalk construction will require extension of the Mill Brook sluiceway as well as modifications to the bridge slope paving. Related work includes minor drainage modifications and upgrades, as well as updated signage and pavement markings.
Location:
  • Town of Webster
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $14,300,876.20
    Estimated Total Federal Participating Construction Cost: $15,018,235.72
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received (as of 03/27/2024 )

    Contracts (2) Progress
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WEBSTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, CMAQ + STBG + Statewide HSIP Total Project Cost = $14,945,008, Design Status = 75%, PM Score 17 out of 27, State & Target funds being used
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $1,600,000.00
    State Cost: $400,000.00
    Total Cost: $2,000,000.00

    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WEBSTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, CMAQ + STBG + Statewide HSIP Total Project Cost = $14,945,008, Design Status = 75%, PM Score 17 out of 27, State & Target funds being used
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,493,600.00
    State Cost: $1,123,400.00
    Total Cost: $5,617,000.00

    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WEBSTER
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, CMAQ + STBG + Statewide HSIP Total Project Cost = $14,945,008, Design Status = 75%, PM Score 17 out of 27, State & Target funds being used
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $6,595,207.20
    State Cost: $732,800.80
    Total Cost: $7,328,008.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/14/2016
    Project Initiation Form PIF Entered 01/14/2016
    Project Initiation Form PRC Submitted 01/14/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    100% Design 100% Package Received 08/25/2023
    100% Design 100% Package Comments to DE 10/05/2023
    25% Design 25% Package Received 10/10/2019
    25% Design 25% Package Comments to DE 01/05/2021
    25% Design Design Public Hearing 10/06/2021
    75% Design 75% Package Received 11/28/2022
    75% Design 75% Package Comments to DE 03/02/2023
    Final Design PS&E Received 03/27/2024
    Consultant Contract Process NTP Issued 08/16/2017