Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ASHLAND- REHABILITATION AND RAIL CROSSING IMPROVEMENTS ON CHERRY STREET
The proposed improvements consist of roadway and pedestrian improvements as a supplemental safety measure to facilitate the implementation of a Railroad Quiet Zone in the town center. Improvements consist of rehabilitation of 750 ft. of Cherry Street and spot improvements on Main Street at the MBTA crossing. The Cherry Street reconstruction will consist of widening Cherry Street to provide a non traversable median in both sides of the railroad crossing. In addition, a sidewalk will be added to this section of roadway, connecting existing sidewalks on either side of the project.
Location:
  • Town of Ashland
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $829,380.60
    Estimated Total Federal Participating Construction Cost: $1,175,303.18
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Comments to DE (as of 08/19/2020 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: ASHLAND
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $1,222,315 (Railroads Crossing/RRHE funding). Earmark of $599,897 (Demo ID MA 262).
  • Category FA - Other Federal Aid
    Federal Cost: $1,053,071.20
    State Cost: $263,267.80
    Total Cost: $1,316,339.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/14/2016
    Project Initiation Form PIF Entered 01/19/2016
    Project Initiation Form PRC Submitted 07/13/2017
    Project Review Committee PRC Tabled 07/20/2017
    Project Review Committee PRC Approved 07/27/2017
    Project Management
    25% Design 25% Package Received 02/04/2020
    25% Design 25% Package Comments to DE 08/19/2020