Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- PARCEL 7/RMV, HAYMARKET STATION AND VENT BUILDING 4
This work includes but is not limited to the following: Waterproofing on exposed garage deck (this condition “is causing leaking into the public market”); Expansion joints in garage; Stairs - poor condition; Fire system control panels (included in RDK study under project 706739); Elevator repairs.
Location:
  • City of Boston
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Pasquale Mele
    Construction Bid Price: $3,997,750.00
    District: District 6

    Contracts (1) Progress
    # 104748 -- Construction Contract
    Haymarket Center Parking Garage Repairs at 110 Sudbury Street (Re-Advertised Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/24/2019
    Contract Information
    Project Designer:
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/15/2016
    Project Initiation Form PIF Entered 01/15/2016
    Project Initiation Form PRC Submitted 01/15/2016
    Project Review Committee PRC Approved 01/25/2016
    Project Status Advertised 07/01/2017
    Project Status Advertised 07/07/2018
    Project Management
    Final Design PS&E Received 06/26/2017
    Final Design PS&E to FAPRO 06/29/2017
    Final Design PS&E Received - Resub 1 05/25/2018