Project Description:
LITTLETON- AYER- INTERSECTION IMPROVEMENTS ON ROUTE 2A AT WILLOW ROAD AND BRUCE STREET
The project involves intersection improvements, including geometric modifications, widening and signalization. Additional improvements involve updated signage and pavement markings.
Location:
  • Town of Ayer
  • Town of Littleton
  • Construction Begins: Autumn 2022
    Resident Engineer: Christopher Deloge
    Construction Bid Price: $3,099,585.24
    District: District 3

    Contracts (2) Progress
    # 120176 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Ayer Road (Route 2A/110) at Willow Road and Bruce Street 99% Complete
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/07/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/25/2016
    Project Initiation Form PIF Entered 01/25/2016
    Project Initiation Form PRC Submitted 01/25/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 02/28/2022
    100% Design 100% Package Comments to DE 03/30/2022
    25% Design 25% Package Received 09/24/2018
    25% Design 25% Package Comments to DE 03/01/2019
    25% Design 25% Package Received - Resub 1 11/17/2020
    25% Design Design Public Hearing 06/15/2021
    75% Design 75% Package Received 07/12/2021
    75% Design 75% Package Comments to DE 08/26/2021
    Final Design PS&E Received 06/29/2022
    Final Design PS&E to FAPRO 08/15/2022