Project Description: |
BOSTON- ROADWAY IMPROVEMENTS ALONG COMMONWEALTH AVENUE (ROUTE 30), FROM ALCORN STREET TO WARREN/KELTON STREETS (PHASE 3 & PHASE 4)
The proposed 1.1 mile project includes full reconstructio of the roadway pavement, sidewalks, curbs and medians. The addition of separated bicycle facilities, retainage of mature trees, drainage upgrades, addition of new urban design and landscape features and traffic signal and lighting upgrades.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Project Manager: | Joshua Bartus |
Estimated Total Contract Cost: | $28,623,514.59 |
Estimated Total Federal Participating Construction Cost: | $31,036,005.80 |
District: | District 6 |
Current Status: | 25% Package Received (as of 09/28/2017 ) |
|
Bridges |
|
|
|