Project Description: |
BOSTON- TUNNEL AND DRAIN LINE REPAIRS ON I-90 (EB & WB) (CRC 11B)
Work consists of multiple phases of construction which will repair/ reline the 42-inch drain line, construct a circular access shaft, complete lateral soil investigations under the I-90 tunnels and perform grouting as needed. This area has experienced considerable settlement since completion of I-90 EB/WB jacked tunnels in 2000 due to thawing of soil in the vicinity of the deep ground freezing zone.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Autumn 2019 |
Project Manager: | Philip Macdonald |
Estimated Total Contract Cost: | $24,307,553.12 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 6 |
Current Status: | This project has been advertised for construction bids. (as of 06/22/2019 ) |
|