Project Description:
PLYMOUTH- KINGSTON- CARVER- PLYMPTON- RESURFACING AND RELATED WORK ON ROUTE 44 (FROM MM 28.8 TO 36.4)
Work on this project consists of mill and overlay on Route 44 between mile markers 28.80 and 36.40
Location:
  • Town of Carver
  • Town of Kingston
  • Town of Plymouth
  • Town of Plympton
  • Construction Begins: Summer 2018
    Resident Engineer: Amy Aveiro
    Construction Bid Price: $8,846,388.00
    District: District 5

    Contracts (1) Progress
    # 102728 -- Construction Contract
    Resurfacing and Related Work (Including 11 Bridges) along a Section of Route 44. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/25/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/29/2016
    Project Initiation Form PIF Entered 01/29/2016
    Project Initiation Form PRC Submitted 01/29/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 11/11/2017
    Project Management
    100% Design 100% Package Received 07/17/2017
    100% Design 100% Package Comments to DE 08/09/2017
    25% Design 25% Package Received 04/18/2017
    25% Design 25% Package Comments to DE 06/28/2017
    75% Design 75% Package Received 04/18/2017
    75% Design 75% Package Comments to DE 06/28/2017
    Final Design PS&E Received 07/17/2017
    Final Design PS&E Received - Resub 1 09/08/2017
    Final Design PS&E Received - Resub 2 10/02/2017