Project Description:
PLYMOUTH- KINGSTON- CARVER- PLYMPTON- RESURFACING AND RELATED WORK ON ROUTE 44 (FROM MM 28.8 TO 36.4)
Work on this project consists of mill and overlay on Route 44 between mile markers 28.80 and 36.40
Location:
  • Town of Carver
  • Town of Kingston
  • Town of Plymouth
  • Town of Plympton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2018
    Project Manager: Andrew Wilkins
    Estimated Total Federal Participating Construction Cost: $11,980,059.63
    Estimated Total Contract Cost: $10,511,356.00
    Funding Provision: This project is planned to be funded through the 2018 Transportation Improvement Program for the STATEWIDE.
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 11/11/2017 )

    Contracts (0) Status
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2018
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: CARVER
    KINGSTON
    PLYMOUTH
    PLYMPTON
    Category: Advertised Projects Constr.
    Budget Section: UNK

  • Construction
  • Category NHPP National Highway System
    Federal Cost: $8,631,936.00
    State Cost: $2,157,984.00
    Total Cost: $10,789,920.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/29/2016
    Project Initiation Form PIF Entered 01/29/2016
    Project Initiation Form PRC Submitted 01/29/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 11/11/2017
    Project Management
    100% Design 100% Package Received 07/17/2017
    100% Design 100% Package Comments to DE 08/09/2017
    25% Design 25% Package Received 04/18/2017
    25% Design 25% Package Comments to DE 06/28/2017
    75% Design 75% Package Received 04/18/2017
    75% Design 75% Package Comments to DE 06/28/2017
    Final Design PS&E Received 07/17/2017