Project Description: |
UPTON- CULVERT REPLACEMENT, MILFORD STREET (ROUTE 140) OVER UNNAMED TRIBUTARY TO CENTER BROOK
Existing dual culvert crossing (30" and 48" diameters), to be replaced with a 6'wx5'hx64'l box culvert. Associated drainage improvements and utility relocations.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2026 |
Project Manager: | Gautam Sen |
Estimated Total Contract Cost: | $1,443,921.50 |
Estimated Total Federal Participating Construction Cost: | $1,598,828.00 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 3 |
Current Status: | Design Public Hearing (as of 08/28/2024 ) |
|