MARLBOROUGH- RESURFACING AND RELATED WORK ON ROUTE 20
The proposed resurfacing extends from just west of Peters Avenue to just east of Wayside Inn Road, for a distance of 2.4 miles. Additional work will include traffic signal upgrades, reconstruction of existing sidewalks, as well as construction of new sidewalk.
Location:
  • City of Marlborough
  • Construction Begins: Autumn 2021
    Resident Engineer: Anthony Maglione
    Construction Bid Price: $15,851,312.50
    District: District 3

    Contracts (2) Progress
    # 114659 -- Construction Contract
    Resurfacing and Related Work (Including Signals and Water Main Replacement) on a Section of Route 20 (Boston Post Road)
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/18/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 05/29/2021
    Project Management
    100% Design 100% Package Received 11/12/2019
    100% Design 100% Package Comments to DE 01/14/2020
    100% Design 100% Package Received - Resub 1 03/18/2020
    25% Design 25% Package Received 10/27/2017
    25% Design 25% Package Comments to DE 01/04/2018
    25% Design 25% Package Received - Resub 1 08/27/2018
    25% Design Design Public Hearing 02/05/2019
    75% Design 75% Package Received 07/02/2019
    75% Design 75% Package Comments to DE 08/29/2019
    Final Design PS&E Received 02/25/2021
    Final Design PS&E Received - Resub 1 04/21/2021
    Final Design PS&E Received - Resub 2 05/13/2021