Project Description:
SOUTH HADLEY- RESURFACING AND RELATED WORK ON ROUTE 116
Work will consist of resurfacing on Route 116 beginning at Ranger Street and extending 1.1 miles northerly to the intersection with Kendrick Street. The improvements to be made are as summarized: Mill and overlay the existing roadway with 12 foot travel lanes and 8 foot buffered bike lanes both sides of the road where feasible; Evaluate the condition of existing sidewalks and wheelchair ramps and replace as required by condition or conformity with ADA requirements; Traffic signal replacement at the intersection with Lyman Street (Route 33) and new sign and pavement markings to accommodate the new construction.
Location:
  • Town of South Hadley
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Aziz Bensoum
    Construction Bid Price: $6,306,158.00
    District: District 2

    Contracts (2) Progress
    # 116951 -- Construction Contract
    Resurfacing and Related Work (Including Signals & Reconstruction of 2 Dams) on a Section on Newton Street (Route 116) 75% Complete
    # 77852 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/15/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 12/11/2021
    Project Management
    100% Design 100% Package Received 03/20/2020
    100% Design 100% Package Comments to DE 04/24/2020
    25% Design 25% Package Received 01/29/2019
    25% Design 25% Package Comments to DE 04/08/2019
    25% Design 25% Package Approved 04/24/2019
    25% Design Design Public Hearing 06/19/2019
    25% Design 25% Plans Complete 04/24/2019
    75% Design 75% Package Received 09/06/2019
    75% Design 75% Package Comments to DE 01/30/2020
    Final Design PS&E Received 03/20/2021
    Final Design PS&E Received - Resub 1 07/28/2021
    Final Design PS&E Received - Resub 2 08/30/2021
    Consultant Contract Process NTP Issued 09/19/2018