Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LANCASTER- HARVARD- LITTLETON- RESURFACING AND RELATED WORK ON ROUTE 2
Work consists of resurfacing on Route 2.
Location:
  • Town of Harvard
  • Town of Lancaster
  • Town of Littleton
  • Construction Begins: Spring 2019
    Resident Engineer: Carmen Ramirez
    Construction Bid Price: $17,986,688.00
    District: District 3

    Contracts (1) Progress
    # 106578 -- Construction Contract
    Resurfacing and Related Work (Including 5 Bridges) along a Section of Route 2 (George W. Stanton Highway) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/21/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 12/08/2018
    Project Management
    100% Design 100% Package Received 10/16/2018
    25% Design 25% Package Received 06/11/2018
    75% Design 75% Package Received 06/11/2018
    75% Design 75% Package Comments to DE 07/24/2018
    Final Design PS&E Received 10/16/2018
    Final Design PS&E to FAPRO 11/19/2018