Project Description: |
ATTLEBORO- NORTH ATTLEBORO- RESURFACING AND RELATED WORK ON ROUTE 1
Work consists of resurfacing and related work on Route 1.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Lyris Liautaud |
Estimated Total Contract Cost: | $12,965,461.00 |
Estimated Total Federal Participating Construction Cost: | $14,076,613.40 |
District: | District 5 |
Current Status: | 25% Package Comments to DE (as of 10/08/2020 ) |
|
Bridges
|
|
|
|