Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FOXBOROUGH- RESURFACING AND RELATED WORK ON ROUTE 1
Location:
  • Town of Foxborough
  • Construction Begins: Summer 2023
    Resident Engineer: Sean Darling
    Construction Bid Price: $8,960,298.25
    District: District 5
    Current Status: The contractor will be placing loam and seed throughout the project. The contractor will also be adjusting drainage structures throughout the project. Before winter shutdown they will patch all the potholes within the project limits. .Normal work hours are Monday through Friday, 7:00 AM to 3:30 pm. Expect periodic lane closures and restrictions. (as of 11/19/2024)

    Contracts (3) Progress
    # 122606 -- Construction Contract
    Resurfacing and Related Work on Route 1 37% Complete
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/12/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor will be placing loam and seed throughout the project. The contractor will also be adjusting drainage structures throughout the project. Before winter shutdown they will patch all the potholes within the project limits. .Normal work hours are Monday through Friday, 7:00 AM to 3:30 pm. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 06/24/2023
    Project Management
    100% Design 100% Package Received 07/11/2022
    100% Design 100% Package Comments to DE 08/29/2022
    25% Design 25% Package Received 07/20/2020
    25% Design 25% Package Comments to DE 09/24/2020
    25% Design Design Public Hearing 11/04/2021
    75% Design 75% Package Received 03/02/2022
    75% Design 75% Package Comments to DE 04/11/2022
    Final Design PS&E Received 11/28/2022
    Final Design PS&E Received - Resub 1 05/23/2023
    Consultant Contract Process NTP Issued 08/15/2018