Project Description: |
FOXBOROUGH- RESURFACING AND RELATED WORK ON ROUTE 1
|
Location: |
|
Construction Begins: | Summer 2023 |
Resident Engineer: | Sean Darling![]() |
Construction Bid Price: | $8,960,298.25 |
District: | District 5 |
Current Status: | Excavating and paving driveways throughout the project limits. Installing required signage per contract. Partial lane closures are expected and controlled by state and local police. Normal work hours are Monday through Friday, 7:00 AM to 3:30 pm. (as of 04/02/2025) |
|