Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SEEKONK- RESURFACING AND RELATED WORK ON ROUTE 44
Work consists of resurfacing on Route 44.
Location:
  • Town of Seekonk
  • Construction Begins: Spring 2021
    Resident Engineer: Erik Trowbridge
    Construction Bid Price: $1,782,326.75
    District: District 5

    Contracts (2) Progress
    # 114155 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 44 (Taunton Avenue) Completed
    # 77849 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/18/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 03/13/2021
    Project Management
    100% Design 100% Package Received 12/18/2020
    25% Design 25% Package Received 08/04/2020
    75% Design 75% Package Received 08/04/2020
    75% Design 75% Package Comments to DE 10/09/2020
    Final Design PS&E Received 12/18/2020
    Final Design PS&E Received - Resub 1 02/24/2021