Project Description: |
CAMBRIDGE- SOMERVILLE- RESURFACING AND RELATED WORK ON ROUTE 28
Work consists of resurfacing on Route 28.
|
Location: |
|
Construction Begins: | Summer 2021 |
Resident Engineer: | Justin Charos |
Construction Bid Price: | $15,033,542.65 |
District: | District 4 |
Current Status: | Lane closures may be implemented as needed to support construction operations project-wide. Rodent control service’s maintenance surveys are ongoing. Squire’s Bridge vaulted sections’ bent repairs are continuing this winter. The initial scope of work for the Highland Ave Bridge structural steel cleaning above the Community Path has been completed. Highland Bridge inspections and drainage repair work is ongoing. (as of 01/11/2024) |
|