Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CAMBRIDGE- SOMERVILLE- RESURFACING AND RELATED WORK ON ROUTE 28
Work consists of resurfacing on Route 28.
Location:
  • City of Cambridge
  • City of Somerville
  • Construction Begins: Summer 2021
    Resident Engineer: Justin Charos
    Construction Bid Price: $15,033,542.65
    District: District 4

    Contracts (3) Progress
    # 114227 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 28 Completed
    # 115744 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 64301 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/28/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 03/27/2021
    Project Management
    100% Design 100% Package Received 01/12/2021
    100% Design 100% Package Comments to DE 01/27/2021
    25% Design 25% Package Received 05/23/2019
    25% Design 25% Package Rejected 06/06/2019
    75% Design 75% Package Received 05/23/2019
    75% Design 75% Package Rejected 06/06/2019
    Final Design PS&E Received 02/12/2021
    Final Design PS&E Received - Resub 1 03/11/2021