CANTON- MILTON- ROADWAY IMPROVEMENTS ON ROUTE 138
Consists of improving the roadway and related work on Route 138.
Location:
  • Town of Canton
  • Town of Milton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $18,115,000.00
    Estimated Total Federal Participating Construction Cost: $18,467,500.00
    District: District 6
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 07/18/2018 )

    Contracts (1) Progress
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Management
    Consultant Contract Process NTP Issued 07/18/2018