Project Description:
PITTSFIELD- LANESBOROUGH- RESURFACING AND RELATED WORK ON ROUTE 8 (FROM MM 44.43 TO MM 47.77)
Project consists of pavement preservation resurfacing on Route 8.
Location:
  • Town of Lanesborough
  • City of Pittsfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2021
    Project Manager: Misrak Sultan
    Estimated Total Contract Cost: $4,098,323.56
    Estimated Total Federal Participating Construction Cost: $3,570,799.04
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the STATEWIDE.
    District: District 1
    Current Status: This project has been advertised for construction bids. (as of 08/28/2021 )

    Contracts (1) Progress
    # 77851 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: LANESBOROUGH
    PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $2,977,581.60
    State Cost: $744,395.40
    Total Cost: $3,721,977.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 08/28/2021
    Project Management
    100% Design 100% Package Received 09/25/2020
    100% Design 100% Package Comments to DE 10/30/2020
    25% Design 25% Package Received 02/28/2019
    25% Design 25% Package Comments to DE 06/11/2019
    25% Design Design Public Hearing 03/11/2020
    75% Design 75% Package Received 04/30/2020
    75% Design 75% Package Comments to DE 06/15/2020
    75% Design 75% Package Rejected 06/02/2020
    75% Design 75% Package Received - Resub 1 06/19/2020
    75% Design 75% Package Received - Resub 2 07/08/2020
    75% Design 75% Package Received - Resub 4 08/31/2020
    75% Design 75% Plans Complete 07/20/2020
    Final Design PS&E Received 02/05/2021
    Final Design PS&E Received - Resub 1 03/26/2021