Project Description:
WESTFIELD- RESURFACING AND RELATED WORK ON ROUTE 10 AND 202
Location:
  • City of Westfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Daniel Wilk
    Estimated Total Contract Cost: $8,322,226.50
    Estimated Total Federal Participating Construction Cost: $8,629,346.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 25% Package Comments to DE (as of 10/18/2021 )

    Contracts (2) Progress
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction - (YOE $9,831,126) 31.5 TEC / 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $8,008,032.80
    State Cost: $2,002,008.20
    Total Cost: $10,010,041.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Management
    25% Design 25% Package Received 07/20/2021
    25% Design 25% Package Comments to DE 10/18/2021