Project Description:
MENDON- RESURFACING AND RELATED WORK ON ROUTE 16
Project limits extend from Taft Avenue in Mendon to the Mendon/Hopedale Town Line, a distance of 1.9 miles. The project involves roadway resurfacing with minor box widening as well as bike and pedestrian improvements. Intersection improvements include two new signals at Hartford Avenue West and Maple Street, and a signal upgrade at North Avenue.
Location:
  • Town of Mendon
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Kimberley Sloan
    Estimated Total Contract Cost: $19,662,590.54
    Estimated Total Federal Participating Construction Cost: $22,800,578.86
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received (as of 09/26/2024 )

    Contracts (1) Progress
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MENDON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Project is AC'd between 2025 & 2026, Total Project Cost = $24,724,764, Design Status = 100%
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $8,800,000.00
    State Cost: $2,200,000.00
    Total Cost: $11,000,000.00

    Planned Federal FY: 2026
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MENDON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Project is AC'd between 2025 & 2026, Total Project Cost = $24,724,764, Design Status = 100%
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $10,989,305.60
    State Cost: $2,747,326.40
    Total Cost: $13,736,632.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Management
    100% Design 100% Package Received 02/23/2024
    100% Design 100% Package Comments to DE 03/29/2024
    25% Design 25% Package Received 08/06/2021
    25% Design 25% Package Comments to DE 08/16/2021
    25% Design Design Public Hearing 09/22/2022
    75% Design 75% Package Received 03/21/2023
    75% Design 75% Package Comments to DE 04/28/2023
    Final Design PS&E Received 09/26/2024
    Consultant Contract Process NTP Issued 07/26/2017