Project Description:
NEWBURY- NEWBURYPORT- SALISBURY- RESURFACING AND RELATED WORK ON ROUTE 1
Work consists of resurfacing on Route 1.
Location:
  • Town of Newbury
  • City of Newburyport
  • Town of Salisbury
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2022
    Project Manager: Eric I Nova
    Estimated Total Contract Cost: $11,973,008.15
    Estimated Total Federal Participating Construction Cost: $12,273,521.05
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Comments to DE (as of 05/18/2021 )

    Contracts (2) Progress
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86787 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NEWBURY
    NEWBURYPORT
    SALISBURY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $7,845,760.00
    State Cost: $1,961,440.00
    Total Cost: $9,807,200.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Management
    25% Design 25% Package Received 03/17/2021
    75% Design 75% Package Received 03/17/2021
    75% Design 75% Package Comments to DE 05/18/2021