Project Description:
NEWBURY- NEWBURYPORT- SALISBURY- RESURFACING AND RELATED WORK ON ROUTE 1
The project begins at the bridge over Mill River, which is on the Rowley/Newbury border. Roadway work shall meet with the existing lateral pavement joint made during a previous Route 1 resurfacing project, (approximate mm 76.546) and extends northerly, ending in Salisbury (mm 83.611). The length of the project is 7.065 miles. Work extends into Pond Street and Low Street for sidewalk reconstruction. No other work on the on/off ramps is proposed. The project shall also include cement concrete pavement installation at the Route 1/Middle Road/Hanover Street intersection, reconstruction of the Newburyport Traffic Circle, traffic signal modifications, pavement widening and other work as required by the Engineer. Related work consists of removing and disposing of guardrail along the mainline; replacing guardrail; proposed MASH approved guardrail end treatments; replacing all grates and covers with bolt down grates and bolt down covers; adjusting, cleaning and rebuilding drainage structures; removing and resetting granite edging; replacing all frames and grates; replacing any broken granite curb and edging; sidewalk and pedestrian curb ramp replacement at intersection of Route 1 and Low St./Pond St.; unclassified excavation; fine grading and compacting; pavement milling mulch for shoulders; removing and resetting signs; placing final pavement markings and incidental items and as required by the Engineer. Bridge work shall include bridge pavement milling and resurfacing, bridge fascia repairs, armor joint repairs, and thrie beam bridge rail retrofit.
Location:
  • Town of Newbury
  • City of Newburyport
  • Town of Salisbury
  • Construction Begins: Spring 2023
    Resident Engineer: Carmen Ilardi
    Construction Bid Price: $17,187,676.85
    District: District 4
    Current Status: The Contractor has completed the following construction activities: drainage, granite curb, concrete and asphalt sidewalks, hawk eye signal mast arm foundations, new traffic island reconfigurations, and the applications of traffic markings for the US Route 1 Newburyport Rotary. (as of 01/08/2024)

    Contracts (3) Progress
    # 119810 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 1 26% Complete
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86787 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/22/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The Contractor has completed the following construction activities: drainage, granite curb, concrete and asphalt sidewalks, hawk eye signal mast arm foundations, new traffic island reconfigurations, and the applications of traffic markings for the US Route 1 Newburyport Rotary.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2016
    Project Initiation Form PIF Entered 02/12/2016
    Project Initiation Form PRC Submitted 02/12/2016
    Project Review Committee PRC Approved 02/12/2016
    Project Status Advertised 08/13/2022
    Project Management
    100% Design 100% Package Received 12/13/2021
    100% Design 100% Package Received 05/03/2022
    100% Design 100% Package Comments to DE 12/28/2021
    25% Design 25% Package Received 03/17/2021
    75% Design 75% Package Received 03/17/2021
    75% Design 75% Package Comments to DE 05/18/2021
    Final Design PS&E Received 07/02/2022
    Final Design PS&E to FAPRO 08/01/2022