Project Description:
BEVERLY- TEMPORARY BRIDGE CONSTRUCTION, B-11-001, BRIDGE STREET OVER BASS RIVER (HALL-WHITAKER DRAWBRIDGE)
Location:
  • City of Beverly
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Robert P Antico
    Estimated Total Contract Cost: $26,420,651.32
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: 100% Package Received (as of 10/28/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/29/2016
    Project Initiation Form PIF Entered 08/04/2016
    Project Initiation Form PRC Submitted 08/04/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Management
    100% Design 100% Package Received 10/28/2024
    25% Design 25% Package Received 04/03/2023
    25% Design 25% Package Comments to DE 05/11/2023
    75% Design 75% Package Received 11/17/2023
    75% Design 75% Package Received - Resub 1 05/31/2024