Project Description:
SALEM- BRIDGE MAINTENANCE, S-01-018 (32T), (ST 114) NORTH STREET OVER (ST 107) BRIDGE STREET & MBTA
Location:
  • City of Salem
  • Construction Begins: Summer 2018
    Resident Engineer: Brian Zilinsky
    Construction Bid Price: $1,706,630.00
    District: District 4

    Contracts (1) Progress
    # 103553 -- Construction Contract
    Bridge Deck Repairs and Related Work (Including Painting) Br. No. S-01-018 North Street (Route 114) over Bridge Street (Route 107) and the MBTA Railroad. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/19/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2016
    Project Initiation Form PIF Entered 03/02/2016
    Project Initiation Form PRC Submitted 06/22/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 03/24/2018
    Project Management
    Final Design PS&E Received 10/25/2017
    Final Design PS&E to FAPRO 03/08/2018