Project Description:
PITTSFIELD- BRIDGE REPLACEMENT, P-10-042, NEW ROAD OVER WEST BRANCH OF THE HOUSATONIC RIVER
The existing culvert at this location is a corrugated metal arch on concrete abutments. A temporary acrow-panel bridge was placed over the deteriorating culvert in the 1990’s. At the present time, the original culvert has completely failed, and a permanent bridge is needed. The proposed bridge replacement will likely be a three-sided frame under significant fill. The anticipated length (not span) will have to be fairly long due to the depth of fill required; and taller headwalls may also be necessary. The project has not yet been formally scoped.
Location:
  • City of Pittsfield
  • Construction Begins: Autumn 2019
    Resident Engineer: Peter Lamarre
    Construction Bid Price: $1,734,102.46
    District: District 1

    Contracts (2) Progress
    # 108248 -- Construction Contract
    Bridge Replacement Br. No. P-10-042 (NEXT Beams) New Road over the West Branch of the Housatonic River Completed
    # 77883 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/12/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/03/2016
    Project Initiation Form PIF Entered 05/06/2016
    Project Initiation Form PRC Submitted 05/06/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 06/22/2019
    Project Management
    100% Design 100% Package Received 01/07/2019
    25% Design 25% Package Received 12/19/2017
    25% Design 25% Package Comments to DE 01/18/2018
    25% Design 25% Package Received - Resub 1 04/09/2018
    25% Design Design Public Hearing 06/07/2018
    75% Design 75% Package Received 08/14/2018
    Final Design PS&E Received 04/16/2019
    Final Design PS&E to FAPRO 05/31/2019
    Consultant Contract Process Scope to DE 02/08/2017
    Consultant Contract Process NTP Issued 03/20/2017
    Consultant Contract Process Workhours Approved 02/24/2017