Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- ROADSIDE VEGETATION MANAGEMENT AT VARIOUS LOCATIONS
Manage roadside vegetation as needed, work to consist of cutting vegetation using various types of equipment not limited to a string trimmer, and 8 and 15 foot mower, guardrail mowers and other tools when needed
Location:
Construction Begins: Summer 2017
Resident Engineer: Michael McGonagle
Construction Bid Price: $668,256.02
District: District 6

Contracts (1) Progress
# 99215 -- Construction Contract
Scheduled and Emergency Vegetation Management at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/07/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/04/2016
    Project Initiation Form PIF Entered 03/04/2016
    Project Initiation Form PRC Submitted 03/04/2016
    Project Review Committee PRC Approved 03/07/2016
    Project Status Advertised 12/10/2016
    Project Management
    100% Design 100% Package Received 10/26/2016
    Final Design PS&E Received 10/28/2016
    Final Design PS&E to FAPRO 11/21/2016