WEST TISBURY- MARTHA'S VINEYARD CORRELLUS BIKE PATH (PHASE 1)
Work on this project includes resurfacing the path at Doctor Fisher Road, Hopps Farm Road and Old County Road path in the Correllus State Forest. Localized repairs will also be included in various locations. The path's surface exhibits extensive cracking and deterioration.
Location:
  • Town of Edgartown
  • Town of West Tisbury
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Michael Zuzevich
    Construction Bid Price: $1,194,022.70
    District: District 5

    Contracts (1) Progress
    # 102064 -- Construction Contract
    Resurfacing and Related Work on the Manuel Correllus State Forest Bike Path (Phase 1). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/09/2018
    Contract Information
    Project Designer: Other
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/11/2016
    Project Initiation Form PIF Entered 03/14/2016
    Project Initiation Form PRC Submitted 04/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 08/26/2017
    Project Management
    100% Design 100% Package Received 06/02/2017
    100% Design 100% Package Comments to DE 07/07/2017
    75% Design 75% Package Received 11/15/2016
    75% Design 75% Package Comments to DE 12/23/2016
    Final Design PS&E Received 08/01/2017
    Final Design PS&E to FAPRO 08/14/2017