Project Description:
MIDDLEBORO- RECONSTRUCTION AND RELATED WORK ON WAREHAM STREET AND WOOD STREET
The work includes improvements to Wareham Street from its' intersection with Center Street and North/South Main Street to Wood Street, a total distance of about 6,400 feet. The proposed work includes pavement rehabilitation, construction of sidewalks and curb ramps to comply with ADA requirements, traffic operation improvements, intersection geometry improvements and stormwater improvements. The work also includes pavement rehabilitation, installation of sidewalks and curbing on Wood Street from Wareham Street to the Nichols Middle School driveway, a distance of about 1,200 feet. The existing traffic signal at Center Street and North/South Main Street (Route 105) will be reconstructed. Bicycle accommodation along the corridor will be in the form of a shared travel lane/shoulder for the portion of the project where on street parking is allowed and a bike lane in the shoulder for the remainder of the project where there is no on street parking.
Location:
  • Town of Middleborough
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Alolade O Campbell
    Estimated Total Contract Cost: $3,667,400.00
    Estimated Total Federal Participating Construction Cost: $4,000,800.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MIDDLEBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $4,320,864 - STBG d) EC Score 61 of 100; h) Project Proponent - Middleboro; i) Status Pre 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,456,691.20
    State Cost: $864,172.80
    Total Cost: $4,320,864.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/14/2016
    Project Initiation Form PIF Entered 06/20/2017
    Project Initiation Form PRC Submitted 06/20/2017
    Project Review Committee PRC Approved 07/20/2017
    Project Management