Project Description:
NEW BEDFORD- CORRIDOR IMPROVEMENTS AND RELATED WORK ON COUNTY STREET, FROM NELSON STREET TO UNION STREET
Work on this project includes roadway milling and resurfacing as well as sidewalk reconstruction and improvements for bicycle accommodation/ This project is intended to address multi-modal accommodation and safety. Bike lanes and upgraded sidewalks that are compliant with the Americans with Disability Act (ADA) are proposed along the project limits. Ground mounted traffic signals along the corridor shall be upgraded with pedestrain activation and emergency pre-emption. Curbing, ramps and crosswalks are also proposed to be improved. New street lighting and drainage maintenance/improvements are also proposed.
Location:
  • City of New Bedford
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Neal Noversa
    Construction Bid Price: $12,234,256.36
    District: District 5
    Current Status: The Contractor has continued to install proposed drainage throughout the Phase 1 area of the project. Roadway conduit crossing work for proposed lighting and traffic signals is anticipated to start the week of 11/17/24.Scheduled work horus are Monday thru Friday 7:30 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 11/18/2024)

    Contracts (1) Progress
    # 124023 -- Construction Contract
    Corridor Improvements and Related Work on County Street, from Nelson Street to Union Street 6% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/17/2024
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The Contractor has continued to install proposed drainage throughout the Phase 1 area of the project. Roadway conduit crossing work for proposed lighting and traffic signals is anticipated to start the week of 11/17/24.Scheduled work horus are Monday thru Friday 7:30 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/30/2016
    Project Initiation Form PIF Entered 05/11/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 02/07/2023
    100% Design 100% Package Comments to DE 03/20/2023
    25% Design 25% Package Received 02/28/2020
    25% Design Design Public Hearing 09/21/2021
    75% Design 75% Package Received 02/04/2022
    75% Design 75% Package Comments to DE 04/20/2022
    Final Design PS&E Received 07/17/2023
    Final Design PS&E Received - Resub 2 08/21/2023