Project Description:
NEW BEDFORD- INTERSECTION IMPROVEMENTS AND RELATED WORK AT ROCKDALE AVENUE AND ALLEN STREET
Work on this project includes minor geometric improvements, traffic signal reconstruction, pedestrian and bicycle accommodation upgrades in compliance with MassDOT’s Healthy Transportation Policy and the Americans with Disabilities Act. The intent of this project is to provide safety and mobility improvements at the intersection of Rockdale Avenue and Allen Street.
Location:
  • City of New Bedford
  • Construction Begins: Summer 2021
    Resident Engineer: Neal Noversa
    Construction Bid Price: $2,067,654.60
    District: District 5
    Current Status: The contractor completed surface course paving project wide on Friday 6/7 /24. Loam and seed along with tree planting installation completed on Friday 6/21 /24. Permanent signage installation is currently ongoing with pavement marking installation tentatively scheduled for 7/2/24. 181 Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 06/25/2024)

    Contracts (1) Progress
    # 114419 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Rockdale Avenue and Allen Street 90% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/16/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/01/2016
    Project Initiation Form PIF Entered 05/16/2016
    Project Initiation Form PRC Submitted 05/16/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 04/24/2021
    Project Management
    100% Design 100% Package Received 12/14/2020
    100% Design 100% Package Comments to DE 01/21/2021
    25% Design 25% Package Received 01/02/2019
    25% Design 25% Package Comments to DE 05/07/2019
    25% Design Design Public Hearing 01/29/2020
    75% Design 75% Package Received 05/07/2020
    75% Design 75% Package Comments to DE 06/29/2020
    Final Design PS&E Received 03/18/2021
    Final Design PS&E to FAPRO 04/12/2021