WINCHENDON- RESURFACING & RELATED WORK ON ROUTE 140, FROM TEEL ROAD TO 430 FT. SOUTH OF ROUTE 12 (1.1 MILES)
This project will begin at Teel Road and extend northerly to 430 ft. south of Route 12 for a total project length of 1.1 miles. As part of this project the roadway will be milled and overlaid. Also included in this project will be the installation of rumble strips, slotted pavement markers, drainage improvements and new signage.
Location:
  • Town of Winchendon
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Matthew Fuller
    Construction Bid Price: $544,859.84
    District: District 2

    Contracts (1) Progress
    # 97782 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 140 (Gardner Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/02/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/29/2016
    Project Initiation Form PIF Entered 04/29/2016
    Project Initiation Form PRC Submitted 05/19/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 09/10/2016
    Project Management
    100% Design 100% Package Received 08/05/2016
    25% Design 25% Package Received 06/09/2016
    75% Design 75% Package Received 06/09/2016
    75% Design 75% Package Comments to DE 06/21/2016
    75% Design 75% Package Comments to DE 07/27/2016
    Final Design PS&E Received 08/05/2016
    Final Design PS&E Received 08/17/2016
    Final Design PS&E to Peer Reviewer 08/08/2016
    Final Design PS&E to FAPRO 08/29/2016