Project Description:
SPRINGFIELD- IMPROVEMENTS ON ST. JAMES AVENUE AT TAPLEY STREET
Statewide HSIP - Project was selected based on the HSIP Top 200 Crash Cluster mapping and in coordination with the District and Regional Planning Agency.
Location:
  • City of Springfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2023
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $5,393,164.71
    Estimated Total Federal Participating Construction Cost: $6,059,158.79
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 100% Package Received (as of 10/31/2022 )

    Contracts (2) Progress
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,697,034.40
    State Cost: $410,781.60
    Total Cost: $4,107,816.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Management
    100% Design 100% Package Received 10/31/2022
    25% Design 25% Package Received 12/12/2018
    25% Design 25% Package Comments to DE 04/12/2019
    25% Design 25% Package Received - Resub 1 01/08/2020
    25% Design 25% Package Received - Resub 1 09/23/2021
    25% Design Design Public Hearing 04/05/2022
    75% Design 75% Package Received 07/15/2022
    75% Design 75% Package Comments to DE 08/19/2022