Project Description:
SPRINGFIELD- IMPROVEMENTS ON ST. JAMES AVENUE AT TAPLEY STREET
Statewide HSIP - Project was selected based on the HSIP Top 200 Crash Cluster mapping and in coordination with the District and Regional Planning Agency.
Location:
  • City of Springfield
  • Construction Begins: Spring 2023
    Resident Engineer: Thomas Doody
    Construction Bid Price: $4,792,940.00
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2

    Contracts (3) Progress
    # 121837 -- Construction Contract
    Improvements on St. James Avenue at Tapley Street
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/08/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Increased from $4,107,816.00 to $6,076,122 via STIP Action 8.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $5,468,509.80
    State Cost: $607,612.20
    Total Cost: $6,076,122.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 04/15/2023
    Project Management
    100% Design 100% Package Received 10/31/2022
    100% Design 100% Package Comments to DE 01/04/2023
    25% Design 25% Package Received 12/12/2018
    25% Design 25% Package Comments to DE 04/12/2019
    25% Design 25% Package Received - Resub 1 01/08/2020
    25% Design 25% Package Received - Resub 1 09/23/2021
    25% Design Design Public Hearing 04/05/2022
    75% Design 75% Package Received 07/15/2022
    75% Design 75% Package Comments to DE 08/19/2022
    Final Design PS&E Received 02/23/2023
    Final Design PS&E Received - Resub 1 03/23/2023