Project Description:
LEOMINSTER- IMPROVEMENTS AT ROUTE 12 (NORTH MAIN STREET) AT HAMILTON STREET; ROUTE 12 (NORTH MAIN STREET) AT NELSON STREET
Statewide HSIP - Project was selected based on the HSIP Top 200 Crash Cluster mapping and in coordination with the District and Regional Planning Agency.
Location:
  • City of Leominster
  • Design Responsibility: Consultant
    Construction Begins: Winter 2021/2022
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $7,657,762.61
    Estimated Total Federal Participating Construction Cost: $8,354,236.03
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 09/04/2021 )

    Contracts (1) Progress
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: LEOMINSTER
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $7,448,129.10
    State Cost: $827,569.90
    Total Cost: $8,275,699.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 09/04/2021
    Project Management
    100% Design 100% Package Received 05/08/2020
    100% Design 100% Package Comments to DE 07/10/2020
    25% Design 25% Package Received 03/11/2019
    25% Design 25% Package Comments to DE 06/10/2019
    25% Design Design Public Hearing 10/01/2019
    75% Design 75% Package Received 12/17/2019
    75% Design 75% Package Comments to DE 02/18/2020
    Final Design PS&E Received 02/11/2021
    Final Design PS&E to FAPRO 08/11/2021
    Final Design PS&E Received - Resub 1 07/21/2021
    Final Design PS&E Received - Resub 2 08/09/2021