Project Description:
SOMERVILLE- SIGNAL AND INTERSECTION IMPROVEMENT ON I-93 AT MYSTIC AVENUE AND MCGRATH HIGHWAY (TOP 200 CRASH LOCATION)
The project includes traffic signal upgrade and safety improvements at Mystic Avenue northbound and Route 28 (Fellsway), at Route 38 southbound (Mystic Avenue) and Route 28 (McGrath Avenue) southbound, at Route 38 southbound (Mystic Avenue) and Route 28 (McGrath Avenue) northbound and at Route 38 southbound at Wheatland Street.
Location:
  • City of Somerville
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: David Shedd
    Estimated Total Contract Cost: $8,526,732.30
    Estimated Total Federal Participating Construction Cost: $8,736,820.20
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 08/17/2024 )

    Contracts (3) Progress
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 08/17/2024
    Project Management
    100% Design 100% Package Received 04/19/2023
    25% Design 25% Package Received 02/03/2021
    25% Design 25% Package Received - Resub 1 07/01/2022
    75% Design 75% Package Received 04/19/2023
    Final Design PS&E Received 06/13/2024
    Final Design PS&E to FAPRO 08/05/2024
    Consultant Contract Process NTP Issued 09/26/2018