Project Description:
SWANSEA- IMPROVEMENTS ON ROUTE 6 (GRAND ARMY OF THE REPUBLIC HIGHWAY) AT GARDNERS NECK ROAD
Work on this project consists of traffic signal upgrades, geometric improvements, improved bicycle and pedestrian accessibility, signs, pavement markings, and/or geometric modifications. The intent of the project is to address safety concerns at this high crash location. Recommendations from the Road Safety Audit will be basis for design.
Location:
  • Town of Swansea
  • Construction Begins: Summer 2024
    Resident Engineer: Erik Trowbridge
    Construction Bid Price: $6,324,310.00
    District: District 5
    Current Status: The contractor plans to continue box widening operations on the southeast corner. Curbing operations on teh southeast corner are expected to begin week ending 4/5/25. This work is expected to last over the next several weeks. A detour of the southern side of Gardners Neck Rd. is to be expected to be utilized for this work. Normal work hours are Monday through Friday 7:00 Am to 3:30 PM. Expecty periodic lane closures and restrictions. Roadway closed to traffic. Detour in place. (as of 03/31/2025)

    Contracts (3) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 126010 -- Construction Contract
    Improvements on Route 6 (Grand Army of the Republic Highway) at Gardners Neck Road 28% Complete
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/24/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 05/18/2024
    Project Management
    100% Design 100% Package Received 02/03/2022
    100% Design 100% Package Comments to DE 05/09/2022
    100% Design 100% Package Received - Resub 1 08/24/2022
    25% Design 25% Package Received 02/21/2019
    25% Design 25% Package Comments to DE 06/04/2019
    25% Design Design Public Hearing 08/12/2020
    75% Design 75% Package Received 11/05/2020
    75% Design 75% Package Comments to DE 02/16/2021
    Final Design PS&E Received 03/14/2024
    Final Design PS&E to FAPRO 04/29/2024