Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SWANSEA- IMPROVEMENTS ON ROUTE 6 (GRAND ARMY OF THE REPUBLIC HIGHWAY) AT GARDNERS NECK ROAD
Work on this project consists of traffic signal upgrades, geometric improvements, improved bicycle and pedestrian accessibility, signs, pavement markings, and/or geometric modifications. The intent of the project is to address safety concerns at this high crash location. Recommendations from the Road Safety Audit will be basis for design.
Location:
  • Town of Swansea
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2024
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $6,983,099.18
    Estimated Total Federal Participating Construction Cost: $6,193,608.50
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: Final Package to FAPRO (as of 04/29/2024 )

    Contracts (2) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SWANSEA
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,604,581.00
    State Cost: $400,509.00
    Total Cost: $4,005,090.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Management
    100% Design 100% Package Received 02/03/2022
    100% Design 100% Package Comments to DE 05/09/2022
    100% Design 100% Package Received - Resub 1 08/24/2022
    25% Design 25% Package Received 02/21/2019
    25% Design 25% Package Comments to DE 06/04/2019
    25% Design Design Public Hearing 08/12/2020
    75% Design 75% Package Received 11/05/2020
    75% Design 75% Package Comments to DE 02/16/2021
    Final Design PS&E Received 03/14/2024
    Final Design PS&E to FAPRO 04/29/2024