Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SPRINGFIELD- IMPROVEMENTS ON ST. JAMES AVENUE AT ST. JAMES BOULEVARD AND CAREW STREET
Statewide HSIP - Project locations will be selected based on the HSIP Top 200 Crash Cluster mapping and in coordination with the District and Regional Planning Agency.
Location:
  • City of Springfield
  • Construction Begins: Spring 2023
    Resident Engineer: Michael DeSimone
    Construction Bid Price: $7,766,615.00
    District: District 2

    Contracts (2) Progress
    # 121499 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of St. James Avenue at St. James Boulevard (Route 20A) and Carew Street 60% Complete
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/17/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 02/25/2023
    Project Management
    100% Design 100% Package Received 08/08/2022
    25% Design 25% Package Received 06/08/2020
    25% Design 25% Package Comments to DE 09/18/2020
    25% Design Design Public Hearing 03/03/2021
    75% Design 75% Package Received 11/02/2021
    Final Design PS&E Received 11/23/2022
    Final Design PS&E to FAPRO 02/06/2023
    Consultant Contract Process NTP Issued 05/16/2018