Project Description:
PEABODY- IMPROVEMENTS AT ROUTE 114 AT SYLVAN STREET, CROSS STREET, NORTHSHORE MALL, LORIS ROAD, ROUTE 128 INTERCHANGE AND ESQUIRE DRIVE
Statewide HSIP - Project locations were selected based on the HSIP Top 200 Crash Cluster mapping and in coordination with the District and Regional Planning Agency.
Location:
  • City of Peabody
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $2,700,000.00
    Estimated Total Federal Participating Construction Cost: $2,960,000.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the STATEWIDE.
    District: District 4
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 05/15/2017 )

    Contracts (1) Progress
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: PEABODY
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,090,240.00
    State Cost: $343,360.00
    Total Cost: $3,433,600.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Management
    Consultant Contract Process NTP Issued 05/15/2017