Project Description:
QUINCY- INTERSECTION IMPROVEMENTS AT ROUTE 3A (SOUTHERN ARTERY) AND BROAD STREET
Statewide HSIP - Project location was selected based on the HSIP Top 200 Crash Cluster mapping and in coordination with the District and Regional Planning Agency.
Location:
  • City of Quincy
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Michael Trepanier
    Estimated Total Contract Cost: $2,700,000.00
    Estimated Total Federal Participating Construction Cost: $2,900,000.00
    District: District 6
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 10/24/2017 )

    Contracts (1) Progress
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/12/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Management
    Consultant Contract Process NTP Issued 10/24/2017