Project Description:
UXBRIDGE TO WORCESTER- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 146
Project is to replace and update guide and traffic signs along Route 140 and intersecting roadways between the Rhode Island/Massachusetts border in Uxbridge and I-290 in Worcester.
Location:
  • Town of Millbury
  • Town of Sutton
  • Town of Uxbridge
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $1,047,000.00
    Estimated Total Federal Participating Construction Cost: $1,123,500.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MILLBURY
    SUTTON
    UXBRIDGE
    WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,132,488.00
    State Cost: $125,832.00
    Total Cost: $1,258,320.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 09/28/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Management