Project Description: |
BURLINGTON TO TYNGSBOROUGH- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF US 3
This project is for the updating and replacement of guide and traffic signs on US Route 3 and intersecting roadways from I-95 (MA 128) in Burlington to the Massachusetts/New Hampshire border in Tyngsborough.
|
Location: |
|
Construction Begins: | Winter 2020/2021 |
Resident Engineer: | Youssef Aboelsaad |
Construction Bid Price: | $6,889,243.30 |
District: | District 4 |
Current Status: | The Contractor, RoadSafe (formerly Liddell Bros.) is continuing pouring the Overhead signs foundations on Rte. 3 NB and Rte. 3 SB. They also began the installation of the Ground Mount Signs. They started installing the Overhead Sign Support Structures and Sign Panels during nightshift operations. (as of 01/23/2024) |
Additional Info: | The Contractor, RoadSafe (formerly Liddell Bros.) is planning to continue pouring the foundations of the Overhead signs supports. They are also planning to continue the installing the Overhead and ground mount Sign. Work will be during the day shift and night shift. (as of 01/23/2024) |
|
Bridges |
|
|
|
|