BURLINGTON TO TYNGSBOROUGH- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF US 3
This project is for the updating and replacement of guide and traffic signs on US Route 3 and intersecting roadways from I-95 (MA 128) in Burlington to the Massachusetts/New Hampshire border in Tyngsborough.
Location:
  • Town of Billerica
  • Town of Burlington
  • Town of Chelmsford
  • Town of Tyngsborough
  • Town of Westford
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Youssef Aboelsaad
    Construction Bid Price: $6,889,243.30
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the STATEWIDE.
    District: District 4
    Current Status: The contractor started mobilizing the work crew and equipment this week. The subcontractor (Soil X) is preforming the soil borings and taken samples to be analyzed. The results will be used for designing the overhead guide sign support system. Cosco, Inc. has also started work on the proposed highway guardrail system. (as of 07/09/2021)
    Additional Info: Soil boring work will be completed by the end of July. (as of 07/09/2021)

    Contracts (1) Progress
    # 113643 -- Construction Contract
    Fabrication, Installation and Removal of Overhead and Ground Mounted Guide and Traffic Signs along a Section of Route 3 4% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/01/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    Planned Federal FY: 2021
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: BILLERICA
    BURLINGTON
    CHELMSFORD
    TYNGSBOROUGH
    WESTFORD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,023,654.40
    State Cost: $1,255,913.60
    Total Cost: $6,279,568.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 10/03/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Status Advertised 12/12/2020
    Project Management
    100% Design 100% Package Received 08/10/2020
    100% Design 100% Package Comments to DE 09/21/2020
    25% Design 25% Package Received 10/22/2019
    25% Design 25% Package Comments to DE 02/05/2020
    25% Design 25% Package Approved 01/29/2020
    75% Design 75% Package Received 08/10/2020
    Final Design PS&E Received 11/09/2020
    Final Design PS&E to FAPRO 11/30/2020