Project Description: |
BURLINGTON TO TYNGSBOROUGH- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF US 3
This project is for the updating and replacement of guide and traffic signs on US Route 3 and intersecting roadways from I-95 (MA 128) in Burlington to the Massachusetts/New Hampshire border in Tyngsborough.
|
Location: |
|
Construction Begins: | Winter 2020/2021 |
Resident Engineer: | Youssef Aboelsaad![]() |
Construction Bid Price: | $6,889,243.30 |
District: | District 4 |
Current Status: | The Contractor started pouring the ground level sign foundations on US Route 3 on the northbound and southbound sides. They also started the installation of regulatory road signs. (as of 07/27/2022) |
Additional Info: | Pouring for the foundations for the Overhead Guide Sign Supports by the end of September. (as of 07/27/2022) |
|