EASTHAMPTON- IMPROVEMENTS AND RELATED WORK ON UNION STREET (ROUTE 141) FROM PAYSON AVENUE TO HIGH STREET (0.36 MILES)
This is a complete streets project that will improve accommodations for all users. The roadway will be resurfaced for improved bicycle use with marked bicycle lanes and sharrows, new and reconstructed sidewalks are proposed for improved pedestrian access, and new wheelchair ramps and crosswalks will be installed.
Location:
  • Town of Easthampton
  • Construction Begins: Spring 2022
    Resident Engineer: Mario Metallo
    Construction Bid Price: $4,023,812.75
    District: District 2

    Contracts (1) Progress
    # 117538 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Union Street (Route 141) 96% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/17/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2016
    Project Initiation Form PIF Entered 05/12/2016
    Project Initiation Form PRC Submitted 05/19/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 03/12/2022
    Project Management
    100% Design 100% Package Received 06/15/2021
    100% Design 100% Package Comments to DE 07/19/2021
    25% Design 25% Package Received 03/08/2019
    25% Design 25% Package Comments to DE 06/10/2019
    25% Design Design Public Hearing 01/13/2020
    75% Design 75% Package Received 11/13/2020
    75% Design 75% Package Comments to DE 01/21/2021
    Final Design PS&E Received 09/21/2021
    Final Design PS&E Received - Resub 1 11/01/2021
    Final Design PS&E Received - Resub 2 11/19/2021
    Final Design PS&E Received - Resub 3 01/03/2022